Jump to the NABCEP notes
Get Solar Certified notes on the NABCEP PV Associate and PVIP exams

NABCEP PVIP study guide

Study guide · job task analysis of December 2017

This NABCEP PVIP study guide takes the PV Installation Professional job task analysis, dated December 2017, one domain per section. Each section says what the domain spans and which code sections and calculations it leans on, in the numbering of the NEC 2017. Near the end, 12 practice questions, three per domain, explain each answer choice.

  • Installation (38%) the largest domain [JTA]
  • NEC 2017 the code edition behind the questions [FAQ] [CBH]
  • 12 practice questions on this page

Domain weights in the PV Installation Professional job task analysis (December 2017).

Number Domain Weight ≈ of the 60 scored
1 System Design 32% ≈ 19 items
2 Installation 38% ≈ 23 items
3 System Commissioning 17% ≈ 10 items
4 Operations & Maintenance 13% ≈ 8 items

Job Task Analysis dated December 2017, the version NABCEP links for the exam. Item counts are rounded from those weights. [JTA] [BE]

Before the domains: which code, which math

Study from the NEC 2017. Several PV provisions have been moved or rewritten in the editions published since, so a rule learned from a newer book can carry the wrong section number or the wrong limit into the exam. Every section reference on this page uses the 2017 numbering.

The arithmetic is short but unforgiving: percentages, temperature corrections, multipliers applied in the right order and rounding to standard sizes. Practice it on a basic scientific calculator, the kind the exam provides on screen.

System Design, 32% of the exam

The domain follows a project from the first conversation to a permit set: the customer's expectations, the project's limits, a site assessment, the mechanical and electrical design, monitoring and communications, the documents and permits, and changes when the site does not match the plan. Much of that work starts from a datasheet value, a site condition or a constraint and ends in a number or a decision.

String voltage and temperature

How many modules go in one string is decided by voltage. Module voltage rises as cells get colder, so the string's open-circuit voltage at the lowest expected ambient temperature is its maximum system voltage. Section 690.7(A) of the 2017 code gives three ways to find it: correct the rated open-circuit voltage with the temperature coefficient in the module's listing instructions; for crystalline and multicrystalline silicon modules, multiply it by the factor in Table 690.7(A); or, for a system of 100 kW or more, use a documented design stamped by a licensed professional electrical engineer. The coefficient method looks like this:

Vmax = N × Voc × [1 + (Tmin − 25 °C) × β]

Here N is the number of modules in series, Voc is the datasheet value at standard test conditions and β is the voltage coefficient written as a decimal per °C. Because β is negative and Tmin is below 25 °C, the bracket comes out above 1. A coefficient published in mV/°C is converted to a fraction of Voc before it goes into the bracket.

Worked example of the string-voltage formula: a 10-module string of modules rated Voc = 45.2 V with a coefficient of −0.27 %/°C, at a site whose design low is −20 °C.

Temperature below standard conditions −20 °C − 25 °C = −45 °C
Correction factor 1 + (−45 × −0.0027) = 1.1215
Corrected module voltage 45.2 V × 1.1215 = 50.69 V
String of 10 modules 10 × 50.69 V = 506.9 V

Compare that string voltage with the inverter's maximum input voltage and with the limit 690.7 sets for the type of building.

Current through the source circuits

In 690.8(A)(1) the maximum current of a PV source circuit equals the parallel modules' short-circuit currents added together and multiplied by 1.25, an allowance for irradiance above standard conditions. Conductors and overcurrent devices are then sized from that current under 690.8(B) and 690.9, which add the continuous-duty factor:

Imax = Isc × 1.25

Isize = Imax × 1.25 ≈ Isc × 1.56

Installation, 38% of the exam

Installation covers the work on site: a safety plan and hazard controls, raceways, electrical equipment, DC and AC conductors, grounding and bonding, the utility interconnection, monitoring hardware, batteries, ground and building mounts, and the modules. Safety tasks in this domain draw on OSHA's construction rules in 29 CFR 1926 and on NFPA 70E for electrical hazards, both on NABCEP's reference list.

Code sections to know by number

  • 690.7 to 690.9: maximum voltage, circuit current and overcurrent protection.
  • 690.12: rapid shutdown of PV systems on buildings. The section sets a voltage and a time limit for conductors outside the array boundary and separate requirements inside it; learn both as the 2017 text states them, since later editions reworked the inside-array options.
  • 690.13 and 690.15: the PV system disconnect and the disconnects that isolate equipment.
  • 690.31: wiring methods. 690.41 to 690.47: system grounding, equipment grounding and the electrode.
  • 690.53 to 690.56: marking and labels.
  • 705.12: the point of connection, with supply-side connections in 705.12(A) and load-side connections in 705.12(B). The 2014 code had the load side in 705.12(D), and the 2020 code moved the supply side to a new 705.11, so older and newer study material cites different numbers.
  • Article 706 for energy storage systems, new in 2017, and Article 480 for storage batteries.
  • 310.15: ampacity, with the correction and adjustment tables and, in 310.15(B)(3)(c), a separate temperature rule for raceways and cables in sunlight on rooftops.

Conductor ampacity under conditions of use

A conductor's table ampacity is reduced for the ambient temperature it runs in and again for the number of current-carrying conductors sharing the raceway:

Iallowed = Itable × ktemp × kfill

The result has to cover the current found under 690.8; check the termination temperature rating as well, because the smaller value governs.

Inverter output and the load-side connection

The inverter output circuit uses the same continuous-duty factor: 125 percent of the inverter's rated output current, rounded up to the next standard breaker size. Where that breaker lands on a panel's busbar, 705.12(B)(2) limits how much current the busbar may see from all sources. One of the options in 705.12(B)(2)(3), which carries conditions of its own, lets the sum of 125 percent of the inverter output current and the main breaker rating reach 120 percent of the busbar rating:

1.25 × Iinv + Imain ≤ 1.2 × Ibus

The 2017 text sets out each option with its conditions; read them all before applying any one of them.

Voltage drop

The code treats voltage drop as a design recommendation rather than a hard limit, but it is a standard calculation for a long DC run. For a two-wire circuit of one-way length L in feet, current I and conductor resistance R in ohms per 1,000 ft:

Vdrop = 2 × L × I × R / 1,000

% drop = Vdrop / V × 100

System Commissioning, 17% of the exam

Commissioning proves that what was built matches the design and the code before the owner takes over. The job task analysis runs through a commissioning protocol, a visual and mechanical inspection, mechanical tests, electrical tests, verifying operation, closing out the project and walking the owner through the system.

The electrical tests are where most of the reasoning sits: polarity and continuity, open-circuit voltage and short-circuit current per string, insulation resistance and witness tests such as anti-islanding. A measurement means little on its own: it is compared with an expected value corrected for the conditions during the test, and the design values at standard test conditions are only the starting point. A reading far from its expected value points to a wiring, module or connection problem in that circuit, and the commissioning protocol decides what to check next.

Operations & Maintenance, 13% of the exam

Operations & Maintenance has three tasks: confirming that the system performs as expected over time, preventive maintenance on a schedule, and corrective maintenance when something fails. In the job task analysis these tasks start from what the technician has in hand, such as a monitoring log, an inverter fault, string readings or a thermal image, and end in a cause found and a repair made safely.

In the field this work rests on records. A baseline taken at commissioning, the monitoring history and the preventive schedule are what a later reading is compared against, which makes keeping those records part of the maintenance work itself. Lockout and tagout, and the electrical safety rules in NFPA 70E, apply to service work on the DC and AC sides as much as to installation.

Design, field, commissioning and O&M items

Score: 0 of 0 picked correctly · 12 items here

Q1 · Commissioning · 17%

A technician will run an insulation resistance test on PV source circuits at the combiner. Which step belongs in the test setup?

One tap per item counts toward the score; opening the key first leaves the item unscored.

Skip ahead to the key and the reasoning

SPDs conduct at test voltage and can be damaged or make the insulation look faulty, so IEC 62446-1 has them disconnected first.

The circuit under test is isolated from the inverter; connecting it would put the test voltage on inverter electronics.

Bonding a conductor to ground shorts out the very insulation path the test is meant to measure.

Test voltage comes from the standard's table for the system voltage, not from a doubling rule.

Q2 · System design · 32%

An inverter's MPPT range starts at 250 V. Modules have Vmp = 34.0 V with a Vmp temperature coefficient of −0.35 %/°C, and cells reach 70 °C on the hottest days. What is the fewest modules per string that stays inside the MPPT range?

Skip ahead to the key and the reasoning

Worked answer: C

Temperature rise above STC 70 °C − 25 °C = 45 °C
Hot module Vmp 34.0 V × (1 − 0.0035 × 45) = 28.6 V
Modules needed 250 V ÷ 28.6 V = 8.7
Fewest modules per string (round up) 8.7 → 9 = 9 modules

7 modules divides 250 V by the STC Vmp of 34.0 V and rounds down, leaving the string short even at 25 °C.

8 modules is enough at STC (250 ÷ 34.0 = 7.4), but heat pulls Vmp down to about 28.6 V per module.

At 70 °C, Vmp = 34.0 V × (1 − 0.0035 × 45) = 28.6 V; 250 ÷ 28.6 = 8.7, which rounds up to 9 modules.

10 modules would also stay in range but is not the fewest; it comes from applying 125%, a current factor, to the 250 V threshold.

Q3 · System design · 32%

Two strings will be paralleled on one MPPT input: string A has 10 modules and string B has 9 of the same model. What happens?

Skip ahead to the key and the reasoning

B has the lower voltage and cannot push current into A; at the shared operating point both strings still deliver forward current.

Parallel strings share one voltage; with one module fewer, B's MPP voltage is about 10% lower than A's, so the tracker settles between them and both lose power.

A single MPPT input has one tracker; separate tracking needs a second input.

Parallel strings add their currents at a common voltage; they do not need equal currents.

Q4 · Installation · 38%

A PV system connects on the supply side of a home's service disconnect. Per NEC 705.31 (2017), where must the overcurrent device protecting the PV conductors be located?

Skip ahead to the key and the reasoning

25 ft comes from the feeder tap rules in 240.21, which do not govern a supply-side PV connection.

Being visible from the meter puts no limit on conductor length, which is what the rule controls.

Protection at the far end leaves the service-side conductors exposed to utility fault current.

705.31 in the 2017 NEC places that overcurrent device within 10 ft of where the PV conductors tap the service, limiting unprotected conductor length.

Q5 · Installation · 38%

When a load-side connection relies on the 120% allowance in NEC 705.12, where must the backfed PV breaker sit on the busbar?

Skip ahead to the key and the reasoning

Beside the main, PV and utility currents could add along the whole busbar.

Center feeding is not the arrangement the 120% allowance assumes.

The allowance depends on position; an arbitrary slot can overload part of the busbar.

Feeding from opposite ends keeps utility and PV currents from adding along the busbar; 705.12 also requires a label so the breaker is not relocated.

Q6 · Commissioning · 17%

An I-V curve trace looks normal near short-circuit current, but the slope near Voc is noticeably shallower than the model curve. Which condition does this shape point to?

Skip ahead to the key and the reasoning

Series resistance (corroded or loose connections, undersized wiring) softens the slope near Voc and pulls the knee in, while the region near Isc is unaffected.

Low shunt resistance tilts the flat region near Isc downward, the other end of the curve.

Shading one module lowers that module's output; it does not explain a softer slope near Voc while the Isc region stays normal.

Low light lowers current across the whole curve, yet the Isc region here matches the model.

Q7 · Commissioning · 17%

A new interactive system passes its final building inspection, but the utility has not yet issued permission to operate. What should the installer do?

Skip ahead to the key and the reasoning

The AHJ approves code compliance, not interconnection; the utility decides when the system may connect.

The building inspection and the utility's interconnection approval are separate; operating in parallel with the grid waits for PTO.

Without PTO the meter may not be set up for export, and parallel operation breaks the interconnection agreement.

PTO is a precondition, not after-the-fact paperwork; unapproved export can cost the customer the interconnection.

Q8 · O&M · 13%

An 8.0 kW (dc, STC) array produced 1,082 kWh in a month when plane-of-array insolation was 165 kWh/m² and horizontal insolation was 140 kWh/m². What was the performance ratio?

Skip ahead to the key and the reasoning

Worked answer: B

Plane-of-array insolation horizontal value not used = 165 kWh/m²
Reference yield 8.0 kW × 165 kWh/m² ÷ 1 kW/m² = 1,320 kWh
Performance ratio 1,082 kWh ÷ 1,320 kWh = 82.0%

18.0% is the share of reference energy lost, the complement of the performance ratio.

Reference yield = 8.0 kW × 165 kWh/m² ÷ 1 kW/m² = 1,320 kWh, and 1,082 ÷ 1,320 = 82.0%.

96.6% uses horizontal insolation, which a tilted array does not receive.

122.0% divides the reference yield by the actual output, inverting the ratio.

Q9 · O&M · 13%

A cracked module in a 12-module string must be replaced, but that model is discontinued. What matters most in choosing the replacement?

Skip ahead to the key and the reasoning

Extra wattage usually brings a higher Imp that the string cannot use, so the bigger module is held back by the others.

A brand name says nothing about electrical match; ratings decide whether the string stays balanced.

Frame size affects mounting, not string performance, and any cooling gain is small next to an electrical mismatch.

Every module in series carries the string current, so a replacement with a different Imp either limits the string or wastes part of its own rating; its Voc must also keep the string in limits.

Q10 · O&M · 13%

Combiner readings show 9.1–9.3 A on five strings and 0 A on the sixth. The sixth string's fuse tests good. What is the logical next check?

Skip ahead to the key and the reasoning

With the fuse good, a Voc reading tells whether the string is open somewhere (0 V) or intact, and points the search to wiring, connectors, or a module.

Firmware acts on the whole input; it cannot zero one string while the others read normally.

Five strings are producing normally, so light is not the problem.

Output lugs carry all six strings; a fault there would affect every string, not one.

Q11 · System design · 32%

An inverter's maximum continuous output current is 48 A. Terminals are rated 75 °C, ambient is 30 °C, and the raceway holds three current-carrying conductors. What is the smallest copper THWN-2 conductor for the output circuit?

Skip ahead to the key and the reasoning

Worked answer: C

Required ampacity 48 A × 1.25 = 60 A
75 °C column check 8 AWG = 50 A < 60 A; 6 AWG = 65 A ≥ 60 A = 6 AWG
Smallest conductor 6 AWG copper = 6 AWG

3 AWG applies 125% twice and also reads the 60 °C column, stacking two errors.

4 AWG sizes for 75 A by applying 125% twice; the inverter output circuit needs it once.

48 A × 1.25 = 60 A, and with 75 °C terminals the 75 °C column applies: 6 AWG copper is rated 65 A.

8 AWG (50 A at 75 °C) covers 48 A but not the 125% continuous-current requirement of 60 A.

Q12 · Installation · 38%

Conductors of two different PV systems share a junction box with a removable cover. Per 690.31(B) of the 2017 NEC, how must each system's conductors be grouped?

Skip ahead to the key and the reasoning

Bundling the systems together is what the rule prevents; each system must be identifiable as its own group.

690.31(B)(2) has each system's ac and dc conductors grouped separately by cable ties or similar means at least once, then again at spacings of 6 ft or less.

Bundling positives and negatives of both systems together mixes the systems; each system's conductors are tied as their own group.

Color marking identifies polarity or circuits, but grouping is a physical tie at set intervals.

Open the full PVIP practice set

Parameter Figure As published Source
Job task analysis in use Job Task Analysis dated December 2017, the version NABCEP links for the exam [JTA] [BE]
Code edition on the exam NFPA 70, the National Electrical Code, 2017 edition. The NEC is the only reference allowed. An electronic copy is provided; candidates may also bring a softbound or spiral-bound code book of any year with highlighting only, no tabs or notes. [FAQ] [CBH]
NABCEP reading list NABCEP’s reference list centers on the 2017 NEC, NFPA 70E, OSHA 29 CFR 1926 and PV design and installation texts [REFS]

From NABCEP's PV Installation Professional job task analysis (December 2017), its certification FAQ, the Certification Handbook (2025 update) and its list of exam references; checked November 22, 2026.

Beyond the domains: quiz, requirements, rules, costs

  • PVIP Who it is for, the three entry requirements, Board Eligible status, recertification
  • PVIP practice test Free practice questions in the four domains, worked code math, a note on every option
  • PVIP exam facts Question count, clock, scaled pass mark, the code on screen, results and retakes
  • PVIP registration Application, approval, booking with Meazure Learning and every fee in one place

JTA PDF and NABCEP's Resource Guide

Where can I find the PVIP job task analysis as a PDF?

NABCEP publishes it on nabcep.org and links it from its Board Eligible page; the version in use is dated December 2017. It lists the tasks under each domain, which makes it a useful checklist next to this page.

Is this the same as NABCEP's PVIP Resource Guide?

No. NABCEP publishes its own resource guide for PV installation professionals, and this site does not reproduce it. This page outlines the job task analysis independently and adds practice items.

What the bracketed tags point to